1: Salient Features Authority National Highways Authority of India
Concession Model Toll
Total Project Cost (as per Authority) Rs. 450 Cr
Agreement Date 25th January 2006
Appointment/ Commencement Date 24th July 2006
Commercial Operation Date 6th April 2010
Concession Period 20 Years from appointment date
2: Technical Details Project Length 24.365 Km
Type of Pavement Flexible for at grade road
No. of Lanes 4 lane (Elevated) and 6 lane (At grade)
Service Road Length 46.796 Km
Toll Plaza 5 No. (4 at Electronic City + 1 Attibele)
Major Bridge NIL
Minor Bridge 1 No.
ROB/ Grade Separator 7 No. (1 RUB + 3 Flyovers + 3 Overpasses) in addition to elevated section
Underpasses 8 No. (Nil VUP + 8 PUP)
Culverts 42 No.